Case Study - Severn Trent Water – Derby

Severn Trent Water – Derby

Severn Trent – Derby

Severn Trent were relocating office staff to be based at a new depot in Derby.  Due to timing and budget constraints Catfoss supplied a modular value engineered solution in line with Severn Trent standard finishes.

The building comprised of office and welfare accommodation across 2 floors and was fitted with a platform lift in order to comply with DDA requirements.


Project Specification

  • Size – 1,000 sqm
  • Scope of Works –
    • Project feasibility
    • Detailed design
    • Bespoke manufacture
    • Ground/infrastructure works
    • Delivery and installation
    • Completion of on-site works
  • Timescales – 20 weeks
  • Build Method – Recycled steel frame modular construction